Skip to main content
Version: 3.9.x

Risk Management

The Risk Analysis section of P4SaMD is where you identify, assess, mitigate, and track risks for your medical device software in compliance with ISO 14971. Risks are managed natively inside the platform, so no external tool is required. Open it by clicking Risk Analysis in the left project sidebar.

Creating a Risk​

Click + New Risk at the top of the risk list, then provide:

  • Title: a concise description of the risk
  • Hazard: the source of potential harm
  • Harm: the damage that could result (e.g., patient injury, data loss)
  • Harm category: one of Patient, Operator, Environment, or Device
  • Initial severity: rated from S1 (lowest) up to the highest level of your product's risk scale. The default scale goes from S1 (negligible) to S5 (catastrophic)
  • Initial probability: rated from P1 (lowest) up to the highest level of your product's risk scale. The default scale goes from P1 (improbable) to P5 (frequent)

Optionally, add the sequence of events (the causal chain from hazard to harm), the hazardous situation (the specific scenario in which harm could occur), and an assignee responsible for the risk.

On save, the risk appears in the list with an automatically assigned display ID (e.g., RSK-0001) and an Identified status.

ISO 14971 Risk Matrix​

P4SaMD automatically computes the initial risk level based on the severity × probability combination. New products start with the ISO 14971:2019 "Option A" 5×5 risk matrix, which you can change for your product (see Risk scale):

Risk LevelMeaning
UnacceptableRisk must be mitigated before the device can proceed
TolerableRisk is tolerable only if reduced as low as reasonably practicable
AcceptableRisk is within acceptable limits
Terminology update in v3.5.0

This zone was previously labelled ALARP. As of P4SaMD v3.5.0, it is called Tolerable everywhere in the platform, and the matrix's severity/probability boundaries were realigned to the ISO 14971 "Option A" matrix. This was a genuine reclassification, not just a rename: some combinations that were previously Unacceptable are now Tolerable, including Severity 5/Probability 1, Severity 4/Probability 2, and Severity 3/Probability 3. See the v3.5.0 release notes for details. You can customize how the three zone names are displayed for your project from the Project Customization settings; this does not affect how risk levels are computed.

Risk Scale​

Every product has its own risk scale. A new product starts with the default scale: five severity levels (Negligible, Minor, Serious, Critical, Catastrophic) and five probability levels (Improbable, Remote, Occasional, Probable, Frequent), with the zones of the ISO 14971 "Option A" matrix. You can adapt it to your own risk policy.

Viewing the scale​

Open Configuration → Product and look at the Risk scale card in the Details tab. Every member can see it. Every risk form, matrix, badge and filter in the product uses the product's levels and their names.

Changing the scale​

Only an Admin can change the scale, at any time.

  1. In the Risk scale card, set the number of severity levels and probability levels, from 2 to 10 each. You cannot go below the number of levels your existing risks already use. The card shows that minimum and the risks that set it.
  2. Give each level a name, up to 40 characters.
  3. Click a cell of the matrix to change its zone, or restore the proposed matrix.
  4. Click save. A review step lists the risks whose level would change and highlights the ones that get worse.
  5. Enter a rationale. It is mandatory when the product already has risks.
  6. Confirm.

Every change is recorded with its rationale in the product's History tab.

P4SaMD warns you when the scale looks unusual, for example when the most severe cell is acceptable or when most cells are acceptable. The warnings are advice and do not block you.

Risks outside the current scale​

A released risk whose stored severity or probability falls outside the current scale keeps its stored values and level. It is shown with grey badges and marked as outside the scale. When you create or edit a risk, or import risks from a CSV file, a value outside the scale is refused with a message naming the allowed levels.

Risk Lifecycle​

Each risk progresses through the following statuses:

Identified → Analyzed → Mitigation Required → Under Control → Verified
↓ ↓ ↓ ↓
Accepted Accepted Accepted Accepted
↓ ↓ ↓ ↓
Transferred Transferred Transferred Transferred
StatusDescriptionAvailable Actions
IdentifiedNewly created risk, not yet fully analyzedAnalyze
AnalyzedRisk has been evaluated; risk level computedStart Mitigation, Accept, Transfer
Mitigation RequiredRisk requires control measures to reduceControl (mark mitigated), Accept, Transfer
Under ControlControl measures are in placeVerify, Accept, Transfer
VerifiedAll control measures verified effectiveAccept
AcceptedRisk formally accepted with documented rationaleNone (terminal)
TransferredRisk responsibility transferred with rationaleNone (terminal)
DeprecatedRisk no longer applicableNone (terminal)

Accepting or transferring a risk requires a mandatory rationale explaining the decision. Verifying a risk requires all linked control measures to be verified first.

Control Measures​

Control measures are the mitigations you put in place to reduce a risk. Add them to any risk from the risk detail view. Mark each control measure as verified once its effectiveness is confirmed.

After control measures are applied, you can record residual severity and residual probability values on the risk to document the reduced risk level.

Risk List and Filtering​

The risk list shows all risks in the active workspace version. The summary columns are display ID, hazard, harm, severity, probability, risk level, residual risk level, status, and assignee.

Summary cards at the top show:

  • Total risks in the version
  • Unacceptable risk count
  • Tolerable risk count
  • Under Control risk count

Filters​

Filter the risk list by:

  • Harm category (Patient, Operator, Environment, Device)
  • Severity level (the levels of your product's risk scale)
  • Probability level (the levels of your product's risk scale)
  • Initial risk level (Unacceptable, Tolerable, Acceptable)
  • Residual risk level
  • Status
  • Assignee

Search and Sort​

Use the search bar to find risks by title or display ID. Sort by sequence number, last updated date, severity, probability, or risk level.

Traceability​

From the risk detail view, you can see and manage links to:

  • Requirements: which requirements this risk relates to
  • Test cases: verification evidence for control measures
  • History: a full audit trail of every change, transition, and rationale

Import and Export​

Import risks from a CSV file for bulk onboarding. Export the current risk register, with active filters applied, for external reports or regulatory submissions.

Deprecating a Risk​

If a risk is no longer applicable (e.g., the related feature was removed), use the Deprecate action from the risk detail view. A rationale is mandatory. Deprecated risks remain in the system for audit traceability but are excluded from active risk counts.